Projects
Tata Nano,Sanand
- Prime Contractor
- Shapoorji PallonJi & Co.Ltd
- Excavation Work
- Footing, Water body, Filling
- Quantum of Work
- Water body 10,00,000 M3
- Footing 2,00,000 M3
- Highlights
- Completed work of water body in 6 months
- Completed work of footing in 3 months
- Prime Contractor
- Shapooriji Pallonji & Co.Ltd
- Road Work
- Bituminous Road, RCC approach,Bituminous Dispatch pad,RCC parking pad
- WMM in shops
- Quantum of work
- 55,00 m3 (Road & Pad)
- 2,00,000 m2 (WMM)
- Highlights
- Completted work in 90 days
Godrej Garden City, Ahmedabad
- Prime Contractor
- Godrej Properties Ltd
- Road Word
- Bituminous Road, Services line under road, Kerbing,ThermoplasticRoad Marking
- Quantum of Work
- 15,000 M2
- Highlights
- Completed work in 45 days
Atreco, Shantigram, Ahmedabad
- Prime Contractor
- Aqualine Propeties Pvt.Ltd.
- Excavation Work
- Footing,Basemet,Filling
- Quantum of Work
- 3,00,000 M3
- Highlights
- Work Completed In 4 Months /li>
IT Park (K. Raheja), Gandhinagar
- Prime Contractor
- Aquline Propeties Pvt. Ltd.
- Excavation Work
- Footing,Basement,Filling
- Quantum of Work
- 3,00,000 M3
- Highlights
- work Completed in 4 months
Iscon Mall, Ahmedabad
- Prime Contractor
- J P Infratructure Pvt. Ltd.
- Excavation Work
- Footing, Basement,Filling
- Quantum of Work
- 1,00,000 M3
- Highlights
- Completed work in 3 days
Alpha Shopping Mall, Ahmedabad
- Prime Contractor
- Alpha C. Corp
- Excavation Work
- Footing, Basement, Filling
- Quantum of Work
- 3,00,000 M3
- Highlights
- Work Completed in 65 days
Spring Dale Retreat, Rethal
- Prime Contractor
- Sandesh Procon LLP
- Excavation Work
- Water Body, Filling
- Quantum of Work
- 18,00,000 M3
- Highlights
- Completed in given time
Applewoods Township, Bopal
- Prime Contractor
- Sandesh Procon LLP
- Road Work
- Bituminous Road, Services line under road, Kerbing Thermoplastic Road Marking
- Quantum of Work
- 40,000 M2
- Excavaton Work
- Footing, Basement & Filling
- Quantum of Work
- 1,00,000 M3
- Highlights
- Work in Progress
List of other Major Projects
| Sr. No. | Name of the Company | Project Executed |
|---|---|---|
| 1 | Shapoorji Pallonji & Co. Ltd. | Tata Motors Ltd., Nano Small Car Project, Sanand. |
| Transformers & Rectifiers India Ltd, Changodar | ||
| DLF IT Park, Gandhinagar | ||
| Areva T & D Project, near Vadodara | ||
| SPRE Project, Vadodara | ||
| Bharat Hotel, Ahmedabad | ||
| 2 | JMC Projects India Ltd. | Mehsana-Nandasan Road Work |
| Godhara Road Work | ||
| Fun Republic Multiplex Theater, Ahmedabad | ||
| IIM (New Campus), Ahmedabad | ||
| 3 | Godrej Properties Ltd. | Godrej Garden City, Ahmedabad |
| 4 | Sandesh Procon LLP | Springdale Retreat |
| 5 | Adani Township & Real Estate Co. Ltd. | Shantigram, AIIM-ATC Campus, Ahmedabad |
| 6 | Alpha G Corp Development Pvt. Ltd. | Ahmedabad City Center, Ahmedabad |
| 7 | K Raheja (Aqualine Properties Pvt. Ltd.) | IT Park, Gandhinagar |
| 8 | Cambay Group | Cambay Resort, Gandhinagar |
| Cambay Hotel, (S.G. Highway & Jivraj park) Ahmedabad | ||
| 9 | Gannon Dunkerly & Co.Ltd. | IIM A Ahmedabad. |
| 10 | Ray Construction | Modasa-Lunawada Road |
| 11 | Dev-Arc Group | Most of the projects in Gujarat |
| 12 | ISCON Group | Most of the projects in Gujarat |